1 2 3 4 5 6 7 8 9 10 11 12
Operation Labour am pm am pm am pm am pm am pm am pm am pm am pm am pm am pm am pm am pm
Start Here
Erect Scaffold Subcontractor
Preparation & Services 1 Builder
Protection 1 Man
Baserail & flashings 2+1 Gang
Adh., Boarding & Mech Fix 2+1 Gang
Beads, Cills & Vents 2+1 Gang
Reinforced Basecoat 2+1 Gang
Primer & Topcoat 2+1 Gang
Remove Protection & Clean 1 Man
Seals & Joints 1 Man
Reinstatement of Services 1 Builder